Compare plating line quotes against one written scope. Align the part families, process stages, accepted output, utility connections and commissioning evidence. Put each supplier's inclusion, exclusion and assumption on the same matrix. Ask for a written clarification when a line item lacks an owner or a testable deliverable.
ES-PRO editorial team · Updated 11 November 2026
Two proposals may show the same number of tanks and different delivery boundaries. One includes rack tooling and wet commissioning. Another includes hardware and an installation supervisor. The totals describe different packages. The plating line cost guide explains why prices vary. This matrix is for comparing proposals you already have. Issue a comparison basis every bidder can quote
Send one revision of the drawings, part mix, finish requirements and facilities plan to all bidders. State which information is provisional and require each bidder to show the effect of any assumption on the design. Record the agreed output in accepted pieces over a defined time window, along with the load and inspection basis.
Require each bidder to return a process list and an interface drawing. The process list explains which operations the proposal includes. The interface drawing shows where a pipe, duct, power connection, physical support or data connection passes from one party's work to another's. Ask for the revision number in the proposal so later clarifications refer to the right drawing.
| | |
|---|
Process route and load range | Stage list, rack types and part envelope | Which families are demonstrated at the quoted load? |
Transfer and line controls | Layout, operating sequence and event records | Which signals and equipment lie outside the panel boundary? |
Site utilities and services | Connection points and design conditions | Who installs and connects beyond each point? |
Rinse, exhaust and collection | Flow diagram and included components | Which upstream capture and downstream interfaces are included? |
Commissioning and release | Test plan, samples and responsible parties | Who provides chemistry, parts, operators and inspection reports? |
| List, quantities and formats | What does the buyer receive at handover? |
Use the equipment buyer's guide to identify the proposed handling format. For a layout question, compare the same loaded rack envelope and path in every proposal. Worked example with two rinse and commissioning offers
Assume Offer A includes rinse tanks, a water supply manifold and an agreed wet production trial. Offer B lists rinse tanks, states “buyer utilities” and includes a dry motion test. Keep both offers visible and mark the gaps.
Ask Offer B where its water boundary ends, whether it provides the flow control and piping inside the line, and what a wet trial would add. Ask Offer A which utility connection conditions it assumes and which parts the buyer must supply. Both suppliers need the same answer about the inspection plan. One quote can include a wet trial without including the buyer's laboratory work.
If the buyer already has a suitable water system and a qualified trial process, it may choose to own part of the gap. Record the owner and cost basis. If the information is still open, label it as open. Converting an unknown into a zero makes the totals appear comparable while hiding the risk.
Close scope questions before ranking the bids
Use one row per deliverable. Enter basis revision · bidder response · included/excluded/option · connection or acceptance point · responsible party · clarification ID · commercial effect. Record the evidence in the bidder's own document and link the clarification to that page.
Once the scope is aligned, compare the quoted prices with documented additions and options. Keep schedule, support and unresolved requirements visible next to the price. Ask the preferred bidder to incorporate accepted clarifications into the controlled offer so the purchase order and acceptance plan refer to the same boundary.
For every open item, ask whether the bid stays valid if that assumption changes. A larger rack envelope can affect tank openings and hoist movement together. A utility handoff moved across the building can change both installation scope and the schedule. Record the linked effects in the matrix and ask the bidder to show which drawing or price line it would revise.
FAQ
Is installation supervision the same as installation?
Ask who supplies the labor, tools, lifting and connections. Record the exact activities the quoted supervision covers.
Can I compare one supplier's wet trial to another supplier's dry test?
Compare the two evidence sets separately. Ask both suppliers to price the same test conditions and identify any buyer responsibilities.
How should I handle an optional wastewater package?
Keep it on a separate bid row. Record where the line ends and which downstream streams and connections the buyer or another contractor owns.