Size a plating line against first-pass accepted pieces in a defined shift. Start with the approved pieces per load and the expected accepted fraction, then check how often the full line can complete a load. Include shared hoist moves, station occupancy, loading, inspection, changeovers and the part mix in the capacity test.
ES-PRO editorial team · Updated 11 November 2026
A supplier can quote a rack every four minutes and still miss demand. Ask what that interval covers, which part family it applies to and how the line handles the next family. A single average can conceal a slow coating stage or an inspection queue.
Build the demand and load record
Write down good pieces required per shift for each part family. List the coating route, usable rack or barrel load, loading and unloading times, and first-pass results from a representative trial. Capture the required output mix as quantities. If a forecast gives a range, ask for a normal mix and a demanding mix so the supplier can price the same cases.
Use the available production time and customer demand to calculate the required pace. The Lean Enterprise Institute definition of takt time provides that demand-side calculation. Separately, track the time the line actually needs to deliver a rack and the time unavailable because of changeovers or other agreed losses. | Why it changes the estimate | |
|---|
Approved loaded pieces by family | Sets how many pieces can enter each run | Fixture revision and qualified load pattern |
First-pass accepted pieces | Establishes output at the agreed inspection point | Load totals and separate held, rejected and reworked counts |
Stage and transfer schedule | Shows whether the stated rack interval is feasible | Station occupancy, hoist moves and drain windows |
Shift time and exclusions | Makes different supplier estimates comparable | Start, stop, changeover and scheduled interruption rules |
For barrel work, use the barrel load factor guide to document the usable load before estimating accepted pieces per barrel. Find the resource that limits completed loads
Draw the route by station. For each station, note how long a load occupies it, how many positions it can hold and which actions share a hoist. A dip may leave the hoist free. A drain over that tank may keep either the hoist or tank occupied. Have the supplier show both on the schedule.
Use station occupancy as an initial check, then verify the sequence. Two tank positions may support the required average load rate and still miss a release interval if the hoist must serve both simultaneously. Add loading, unloading and inspection to the same timeline. If the shop stops releasing racks when inspection space fills, that queue affects finished output.
Work through a mixed shift
In this hypothetical shift, 420 minutes are available for the two families, including their shared changeover. Family A needs 480 first-pass accepted pieces and averages 24 accepted pieces per qualified load. Family B needs 270 and averages 15. Round the required loads up by family when the division leaves a fraction.
| | |
|---|
| | |
Expected accepted pieces per load | | |
Loads required in the example | | |
Sustained load interval from proposed sequence | | |
Illustrative running time | | |
The two runs use 376 minutes at the proposed intervals. A 30-minute changeover brings the estimate to 406 minutes, leaving 14 minutes of margin. If Family B's accepted average drops to 13, it needs 21 loads. Three more loads add 36 minutes and the estimate becomes 442 minutes. This estimate assumes the stated intervals cover completed loads and treats start-up, drain-down and other losses according to the agreed shift boundary.
Ask for a mixed-run schedule or trial before accepting the capacity. If the last racks must clear inspection before shift end, demonstrate that condition. If the plant carries work between shifts, write down how it allocates completed output.
Put a capacity test in the RFQ
Give each bidder the same part drawings, forecast mix, approved load conditions, time window and inspection rules. Ask them to return a station schedule and show what happens when one expected input changes. The line setup checklist provides the broader scope, and the line layout guide covers material flow and access. Record the test basis in one row per part family: route · demand · qualified pieces/load · first-pass result · required loads · validated interval · limiting resource · evidence owner. Then record the order of runs and all time reserved for switching between them.
FAQ
Can I use the longest immersion time as the rack interval?
Use it as one station input. Parallel positions, hoist conflicts and transfer constraints determine the feasible release sequence.
Should repaired parts count toward first-pass output?
Count them in a separate recovered-output figure. The first-pass figure counts pieces accepted without rework at the agreed point.
Which part family should the supplier demonstrate?
Use the mix in the purchase basis and include a demanding family that exercises the identified constraint.
Discuss line capacity